Resource Usage Data in P6 Professional Does Not Match the Database Resource Assignment Table (Doc ID 2098242.1)

Last updated on FEBRUARY 12, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.1.0.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.1.0.0 and later
Primavera P6 Professional Project Management - Version 15.1.0.0 and later
Information in this document applies to any platform.

Symptoms

When querying the database to view the amount of resource hours for a specific time period, this does not match the data displayed in the Activity Usage Spreadsheet or Resource Assignments Spreadsheet in P6 Pro Client.

Spread data does not match when comparing the Resource Assignments Spreadsheet in P6 Web and/or P6 Pro against the database.

Budgeted or Actual Hours do not match when comparing the values in P6 Pro against the tables in the database.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms