Assign Time Set to Incorrect Value in Current Assignments Table When Crew is Suspended. (Doc ID 2100670.1)

Last updated on JULY 12, 2016

Applies to:

Oracle Utilities Network Management System - Version 1.12.0.1 to 1.12.0.3 [Release 1.12]
Oracle Network Management for Utilities - DMS - Version 1.12.0.1 to 1.12.0 [Release 1.12]
Information in this document applies to any platform.

Symptoms

When suspending a crew in the Active Job Info menu, CREW_ASSIGNMENTS.WHEN_ASSIGNED gets set to 1/17/1970.

Steps to reproduce:

1. Log in and take authority
2. Highlight an active event in Work Agenda and assign/dispatch a crew
3. Open the Active Job Info tool for the crew dispatched in step #2, click the "Suspend Crew" button & click "OK".
4. After the crew has been suspended, open the "Crew Info" tool for the crew and review the "Current Assignments" table - notice that the Assign Time column is displaying "01/17/70".

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms