Goal

Is it possible to have the order in which activities are selected determine the order in which they are linked in the Web?

In the Professional Client, if multiple activities are selected using the Ctrl key, the order in which they are selected determines the order in which they are linked when "Link Activities" is selected. Is this possible within P6 Web?

Solution