Apply Actuals Feature Does not Act Same in EPPM As in PPM.

(Doc ID 2101389.1)

Last updated on FEBRUARY 02, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.3 to [Release 8.3]
Primavera P6 Enterprise Project Portfolio Management - Version to [Release 15.1 to 15.2]
Information in this document applies to any platform.


Apply Actuals does not work exactly same in P6 Client when connecting to PPM DB and EPPM DB.

Apply Actuals should work in same way.

The issue can be reproduced at will with the following steps:
1. Login to P6 Client.
2. Create a Project with 5 Activities, set them with 5 days duration, link them with FS relationships.
3. Schedule it on 21-Apr-15.
4. Apply Actuals on 10-May-15, found the first 3 Activities are moved to 11-May-15 in PPM DB, while not moved in EPPM DB.
5. If enable the Auto Compute Actuals, repeat this test above, then the result is same in both sides.

The issue has the following business impact:
Due to this issue, users cannot get same result when Apply Actuals in PPM DB and EPPM DB.


Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms