EBS: PS: PS Solve Results In Activities Starting Within a Delay Events

(Doc ID 2101496.1)

Last updated on MARCH 30, 2017

Applies to:

Oracle Production Scheduling - Version 12.2.5 to 12.2.5 [Release 12.2]
Information in this document applies to any platform.

Symptoms

Issue in PS 12.2.5 Standalone
Application: PS Engine
----------------------------

PS solve results in an activity starting within a delay event

EXPECTED BEHAVIOR
-----------------------
No activity should start within a delay event.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Open PS model
2. Solve the PS model
3. Verify that PS solve results in an activity starting within a delay event


Changes

 n/a

Cause

Sign In with your My Oracle Support account