After Updating Existing Hours in Timesheets the Actual Labor Units for an Activity in P6 Analytics Do Not Reflect the Changed Value (Doc ID 2101791.1)

Last updated on JANUARY 29, 2016

Applies to:

Primavera Data Warehouse - Version 15.1.0.0 and later
Information in this document applies to any platform.

Symptoms

After updating existing hours in Timesheets the actual labor units for an activity in P6 Analytics do not reflect the changed value.
For example, a resource had charged 66 hours on a day. After the Timesheet was submitted the value was changed to 6 hrs. The STAR ETL process was run after the new change was made, but the value in P6 Analytics remains 66 hours instead of the updated value of 6 hours.

Cause