Symptoms

12.1.3.9 in Production

PROBLEM
-------------
User updated a planned order implement date from December 9th to November 12th and when releasing the planned order and then reviewing the
PO the user found that the need by date on the planned order was November 11th.


STEPS
--------
Workbench update implement date.
Release.
View purchase order.