Actual Dates Change Back to the Original Dates After Being Updated (Doc ID 2103399.1)

Last updated on APRIL 05, 2016

Applies to:

Primavera P6 Professional Project Management - Version 15.2.2.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 15.2.2.0 and later
Information in this document applies to any platform.

Symptoms

On : 15.2.0.0 version

ACTUAL BEHAVIOR
---------------
Actual start and actual finish dates of the activity change back to the original dates after updating the actual dates.

EXPECTED BEHAVIOR
-----------------------
The actual dates should keep the value as specified.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. import the attached XER file.
2. change the "Actual start" to 2015-Aug-10.
3. change the "Actual finish" to 2015-Sep-17.
4. notice that the actual dates change back to the original date.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot update actual dates.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms