EBS: PS: Solver Crashes With Pre Build Policy --> Dynamic Resource Allocation, Solve Strategy (Doc ID 2104790.1)

Last updated on MAY 23, 2017

Applies to:

Oracle Production Scheduling - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

Issue in PS 12.2.4 C648
Application: PS Engine
----------------------------

When attempting to solve the model with build strategy of Pre build Policy --> Dynamic Resource Allocation, the PS application gets crashed

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Open the PS model
2. Set the solver option with Build strategy --> Pre Build --> Dynamic Resource Allocation
3. Solve the model & verify that PS application gets crashed

Cause