Activity Dates Not Transferred Correctly From P6 to EBS using Gateway (Doc ID 2106574.1)

Last updated on FEBRUARY 29, 2016

Applies to:

Primavera Gateway - Version 15.2.0.0 and later
Information in this document applies to any platform.

Symptoms

On Primavera Gateway after a P6 to EBS synchronization it has been noticed that this although it completes successfully, the Activity Dates have not been transferred correctly in EBS.
Normally the Activity Dates should be the same at sources (P6) and at destination ( EBS ).


Cause