EBS : PS: WO Lateness Highlighting: Only Highlights when Request Date Is Violated. (Doc ID 2106710.1)

Last updated on MARCH 01, 2019

Applies to:

Oracle Production Scheduling - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.5 version,
Production Scheduling (PS) 12.2.5

In cases where Target Completion Date is populated, the lateness highlighting is currently influenced and partially driven by the Target Completion Date instead of the Request Date.

Note that the Target Completion Date is essentially only used to guide the solver. The business relevant date is the Request Date, and this is the one to be focused on when doing Lateness Highlighting.

Changes

 N /A

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!