Activity End Dates Adjusted After a EBS to P6 Synchronization in Gateway (Doc ID 2108329.1)

Last updated on FEBRUARY 25, 2016

Applies to:

Primavera Gateway - Version 15.2.2.0 and later
Information in this document applies to any platform.

Symptoms

After successfully running a synchronization from EBS to P6 using Primavera Gateway some activity dates appear in P6 as one day prior to the dates in EBS.

Activity Planned Finished Date is moved to the end of the previous working day when time portion of the date is 00:00:00.

Example:

EBS Activity PlannedFinishedDate P6 Adapter Request P6 Activity PlannedFinishedDate
25-Feb-16 00:00:00 (Thursday) 25-Feb-16 00:00:00 (Thursday) 24-Feb-16 16:00 (Wednesday)
29-Feb-16 00:00:00 (Monday) 29-Feb-16 00:00:00 (Monday) 26-Feb-16 16:00 (Friday)

Cause