Project Close Option is Enabled When An EPS Is Selected and Right Clicked and There Are No Projects Open.

(Doc ID 2108519.1)

Last updated on JULY 05, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.1.0.0 and later
Information in this document applies to any platform.

Symptoms

The command "Close" (right click) stays active on an EPS level even if no Project is opened.

This does not apply to the "Close All" option.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1. Open P6 Projects, EPS tab.

2. Select any EPS and right-click mouse when there are no Projects open.  Close option showing as enabled in menu.

Cause