Enhancement Request: Is It Possible To Import New Resources Via XLS Import in the Pro Client
(Doc ID 2109686.1)
Last updated on APRIL 06, 2020
Applies to:
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.2.4.0 and laterPrimavera P6 Enterprise Project Portfolio Management - Version 8.0 and later
Primavera P6 Professional Project Management - Version 8.0 and later
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
When attempting to Import an XLS file using "Resources", the next screen of the Import process does not allow for selecting a Project (blank window).
EXPECTED BEHAVIOR
-----------------------
The Project list will appear to allow the user to select a Project to update.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. File, Export.
2. Spreadsheet - XLS.
3. Select option for "Resources".
4. Complete the Export process.
5. Manually edit the XLS file to include new Resources.
6. File, Import.
7. Spreadsheet - XLS.
8. Select option for "Resources".
9. Complete the remaining Import options.
Note that the new Resources added to the XLS are not imported.
BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot create new Resources via XLS Import.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |