Routing Resource Usages Converted Into Hours In ASCP Plan? (Doc ID 2115295.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.4 and later
Information in this document applies to any platform.

Goal

We are implementing VCP with JDE.
While defining resource usages in JDE, we define them with time basis as Hour, Minute or Seconds.
This data gets collected correctly in VCP as we can see routing resource usage in Hrs, Mins or Seconds in the collected data.
However, when we run the plan, all these usages are converted into Hours. This causes many smaller value usages (e.g. 10.548 sec/unit) to become zero in ASCP plan.

How can we ensure that routing usages are honored as is from collected data into ASCP plan?
 

Solution