Symptoms

On : 12.1.3.8 version, Release Planned Orders To EBS

PS 12.1.3.8

PS internally generates Routing that has incorrect Quantity Remaining for Co-Products as shown on the Produced Items tab of the Work Order Editor.

As a result PS thinks there is no supply for co-product items and generates a Production Recommendation (using the routing from the collected data) to create the needed supply. This Production Recommendation is not really needed and it throws off the timing of the PS schedule by the number of days required to produce the Production Recommendation.

Changes

 n/a

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution