EBS: PS : PS Work Order Package Generates Incorrect Quantity Remaining For Co-Products (Doc ID 2118870.1)

Last updated on JULY 11, 2017

Applies to:

Oracle Production Scheduling - Version 12.1.3.8 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3.8 version, Release Planned Orders To EBS

PS 12.1.3.8

PS internally generates Routing that has incorrect Quantity Remaining for Co-Products as shown on the Produced Items tab of the Work Order Editor.

As a result PS thinks there is no supply for co-product items and generates a Production Recommendation (using the routing from the collected data) to create the needed supply. This Production Recommendation is not really needed and it throws off the timing of the PS schedule by the number of days required to produce the Production Recommendation.

Changes

 n/a

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms