For 'Intransit Shipments' 'Sugg Order Date' Is Updated At Plan Run , Thus For The Exception "Order With Compression Days" The Number Of Days Is Increased (Doc ID 2120536.1)

Last updated on JANUARY 23, 2023

Applies to:

Oracle Materials Requirement Planning - Version 11.5.10.2 and later
Information in this document applies to any platform.

Goal

Issue :

For 'Intransit Shipments' 'Sugg Order Date' is Updated At Plan Run to plan execution date , thus for the exception "Order With Compression Days" the number of days is increased .

By having this number incremented, is causing confusion to the planners in identifying real exception with this exception, which is not "a true" one . 

Expectations :

'Sugg Order Date' shouldn't be changed at plan run , as this is already on it it's way/being shipped to the Organization, thus the Compression Days will stay the same - and planner shouldn't be confused by this exceptions.

 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.