When Not Showing Time (24/7 Calendar) and Updating Scheduled Finished Date +1 Extra Day Ahead is Selected.

(Doc ID 2123415.1)

Last updated on MAY 03, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.3.3.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 8.3.3.0 and later
Primavera P6 Professional Project Management - Version 8.3.3.0 and later
Information in this document applies to any platform.

Symptoms

When an in-progress or not-started activity assigned to a 24 x 7 calendar has its Finish Date manually edited using the calendar selector upon selecting a finish date the actual date entered is +1 day more.
-----------------------
The issue can be reproduced at will with the following steps:
1. Select any not started or in-progressed activity (Actual Start only) assigned to a Global 24/7 calendar (7 days, 24 hours days)
2. Select and edit the Finish Date calendar and set a new finish date exactly 1 day ahead, e.g., finish date 04-May-2015 and change to 05-May-2015.
3. After selecting the OK the finish date jumps 1 extra day ahead to 06-May-2015.

Cause

Sign In with your My Oracle Support account