Sugg Due Date Differ From the Date Required of Component of Phantom (Doc ID 2123508.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

ACTUAL BEHAVIOR:
Users run unconstrained ASCP plan. If there are any components under the Phantom item in Operation Sequence:20 in a discrete job, the Sugg Due Date of the component of Ope Seq:20 in ASCP is set to Date Required of Operation Sequence:10 in the JOB.The Operation Sequence of the component item is 1 in Phantom BOM, and there is no routing in the Phantom. In BOM Parameter, Inherit Phantom Op Seq is Yes.

EXPECTED BEHAVIOR:
The Sugg Due Date of the component of Ope Seq:20 in ASCP should be set to Date Required of Operation Sequence:20 in the JOB.

Steps:
1. Start date of Ope Seq 10 is set to 10-Feb. Start date of Ope Seq 20 is set
to 9-Mar.
Discrete Jobs > operations
(T)Dates
Seq Start date
10 2016/02/10 08:10:00
20 2016/03/09 08:10:00

2. Date Required of Ope Seq 10 is set to 10-Feb. Date Required of Ope Seq 20
is set to 9-Mar.
Discrete Jobs > Material Requirement
(T)Main
Op Date Required
10 2016/02/10 08:10:00

Op Date Required
20 2016/03/09 08:10:00

3. Data collection and launch ASCP

4. In ASCP result, Sugg Due Date of the component of Ope Seq 20 is set to
10-Feb, which is Date Required of Ope Seq 10.

- ASCP Supply/Demand
Item Order Type Sugg Due Date
Component of Ope Seq 20 Work Order Demand 2016/02/10 08:10:00

 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms