Schedule Comparison Feature In Visualizer Hangs When Comparing Against Large Projects (Doc ID 2126913.1)

Last updated on JULY 08, 2016

Applies to:

Primavera P6 Professional Project Management - Version 16.1.0.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
When comparing projects with more than 3000 activities, the visualizer application freezes or hangs.

EXPECTED BEHAVIOR
-----------------------
Visualizer should finish the schedule comparison.


BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot compare projects.

Cause