EBS - PS: PS Does Not Considers Existing On Hand Supplies Before Utilizing Future Purchase Orders, Why ? (Doc ID 2129512.1)

Last updated on MARCH 30, 2017

Applies to:

Oracle Production Scheduling - Version 12.1.3.9 and later
Information in this document applies to any platform.

Goal

Query in PS 12.1.3.8
Application: PS Engine
-----------------------------------------------------------------------------------------------------------
There is enough On hand qty available but why PS looks for the PO's which will be received on later dates (04/02/2016) & why don't it consider the available inventory to schedule earlier?
 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms