12.2.5 - WIP Mass Load Has Incorrect Completion Date

(Doc ID 2130651.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.5 and later
Information in this document applies to any platform.


Both EBS and VCP instance have
VCP 12.2.5 / R12.SCP_PF.C.delta.6 patch - PLUS Mandatory Patch #2 - 22493520

Select all for release fails to load WIP jobs correctly and fails with error.
Single planned order. released normally without issue.

When we release the planned orders from ASCP planning workbench…. The "Suggested Due Date" is at the end of the day 23:59:00.
But the WIP Mass Load reverts the Completion Date/Time to 00:00 of the same day.
All our discrete jobs are only few hour jobs.
Since they are intra-day jobs, with Start Date later than the Completion Date, all the WIP Mass Load are completing with error.

Reproduced internally
12.2.5 - donovan-1225.us.oracle.com
Org M1

Small routing
DGfset forecast

Constrained EDD plan - DGaps1a
Minute buckets for 30 days

Per customer update it appears to be an issue when using /Plan / Select all for release
-- this invokes different code path - instead of MSCPRELB.pls
we use MSC_SELECT_ALL_FOR_RELEASE_PUB MSCSARPB.pls 120.22.12020000.4

Duplicated the issue
- release 4 planned orders using Select all for release and all error.
- Then run plan again (without collections to collect the new jobs)
- then release same job as a single order and it works fine.


Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms