How to Fix Finacial Periods That Have Been Stored Before the Actual Start of the Activity or Resource (Doc ID 2135823.1)

Last updated on SEPTEMBER 28, 2023

Applies to:

Primavera P6 Professional Project Management - Version 15.1.0.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.1.0.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 15.1.0.0 and later
Information in this document applies to any platform.

Symptoms

Project Costs Not Calculating Properly. Cost At Completion, Remaining Cost and Actual Cost to Date do not properly calculate as Actual This Period is adjusted. It appears there is cost associated with line items from previous pay periods that should be not there, and were not there prior to any import.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
 Query to find which values have been stored before the Activity or Resource Assignment Start
 Run the following queries to remove these erroneous records
References