You are testing this integration from Primavera P6 with ASCP. The demand integration from P6 to ASCP completes successfully. This is validated by the P6 project team. How do you see this demand in the ASCP plan?

You have created a Master Demand Schedule (MDS) in the EBS test instance. That MDS has attached to it two items, each also attached to a Project Number and a Task. That MDS has been brought into Primavera and you have also collected this to VCP. You have attached the MDS to our ASCP plan, run your plan and you see the two items with the MDS demand, project and task. But your counterpart in the Primavera P6 area has spoken to your Product Mgt for Primavera and they are saying that the ASCP plan does not yet have the MDS Demand from Primavera P6. You are not sure of the exact steps to get this demand to ASCP from P6.

Are there steps missing on the VCP side? Are there required configurations in order for VCP to see the P6 demand?

Steps taken
1. Load an MDS in EBS that includes project number and Task information.
1. Ran a Complete Refresh Data Collection, including Master Demand Schedule (MDS).
2. Attached the MDS name to Org Code CRP:US1 in the ASCP plan options.
3. Launched the ASCP plan. Once the plan completes you see the two items with the MDS demand, project and task in the Workbench.
 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms