Change Over Time Is Collected, But Is Missing In The Plan Output (Doc ID 2145793.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

12.2.4.1

PROBLEM
-------------
We have Change Over times collected for the resources but plan is not considering the change over time for one of the Resources 586Line1 and 586Line2

STEPS
--------
Open collections workbench - drill to resources
query up resource
then click on Changeover Times and see Changeover Duration populated for all lines

Now run plan and open Planner workbench
drill to resources
query up resource
then click on Changeover Times and see Changeover Duration has ZERO populated for many lines.

EXPECTED BEHAVIOR
----------------------------
Changeover times should appear in the plan output and be used properly

BUSINESS IMPACT
----------------------
cannot use this functionality

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms