Euro Symbol Does Not Display in CSV File

(Doc ID 2146639.1)

Last updated on MARCH 09, 2017

Applies to:

Primavera P6 Professional Project Management - Version 15.2.6.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
-------------
Euro Symbol does not display correctly when you run a report to CSV.

EXPECTED BEHAVIOR
-----------------------
Euro Symbol to display correctly when running a report to CSV.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Log into P6 client.

2. Go to Edit, User Preferences, Currency tab. select Euro and select shot currency symbol.

 



3. Open a Project and go to the Activities View. Make sure one Activity has cost assigned to the Activity.

4. Go to Tools, Report Wizard and create a Report that is going to display cost.

5. Run the Report using the ASCII Text file format.




Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms