Unable to Create New EPS Activity Codes as an Administrator (Doc ID 2147408.1)

Last updated on JANUARY 30, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.3.1.0 and later
Information in this document applies to any platform.

Symptoms

Unable to create a new EPS Activity Code from the Activity Details window.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
Please ensure there is a Activity Code definition for the EPS the Project is under.
1. Open a Project.
2. Navigate to the Activities View.
3. Select Activity Details Window on bottom.
4. Select Codes tab if not present (right-click in Activity Details window and select Customize Activity Details, Codes).
5. Select assign.
5. Select EPS.
6. Notice the Add Code option is grayed out.


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms