Double Values In Compare Plan Mode (Doc ID 2147928.1)

Last updated on JUNE 29, 2017

Applies to:

Oracle Rapid Planning - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

Using Rapid Planning / Compare Plans
On VCP 12.2.5.1
When attempting to Compare Plans,
find that the dependent demand quantities for a given item is doubled in every time bucket of the Material Plan.

EXPECTED BEHAVIOR
-----------------------------------
Expect that the dependent demand quantities for a given item not be doubled.

-- Steps To Reproduce:

Customer states the issue can be reproduced at will at customer site with the following steps:
1. (R) Supply Chain Simulation Planner
2. Review the Material Plan for Plan 00RP_PROD Org EBS:WH2 Item SUSH31512 to see
a Dependent Demand quantity of 43469 in the 5/17/16 time bucket.
3. Review the Material Plan for Plan NO_FDS Org EBS:WH2 Item SUSH31512 to see
a Dependent Demand quantity of 43469 in the 5/17/16 time bucket.
4. Compare Plan Mode between 00RP_PROD and NO_FDS Org EBS:WH2 Item SUSH31512 to see
a Dependent Demand quantity of 86938 in the 5/17/16 time bucket for each plan.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms