EDD Plan Suggesting Re-schedules For FIRM Sales Orders (Doc ID 2148741.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3.8 and later
Information in this document applies to any platform.

Symptoms

12.1.3.8
with EXE from 22852248

PROBLEM
-------------
SCO - EDD without DS

Plan Suggesting Reschedules for FIRM Sales orders,

STEPS
--------
Plan is 60 days / 4 weeks / 2 periods
Planning TF and Demand TF checked
Reservation level Planning group / Hard pegging level - Project

Checked pegging and item setups
All related items have planning time fence days = 1, but planning time fence date - 21-JUN
-- could not find firm order which would make this happen.

Related items from pegging with planned orders
COM-HO*50025263 / 6/30/2016 0:00
EPS-SO*50025265 / 6/30/2016 0:00
CXX38*50025267 / 7/1/2016 0:00
COM-SP*50025261 / 6/29/2016 0:00
COM-HB*50025255 / 6/29/2016 0:00
COM-TK*50025257 / 6/29/2016 0:00
COM-ST*50025259 / 6/29/2016 0:00
4110123
4110227
4115464
SRC_RUSSIA
SP1*50009421
SP2*50009423

These items have start date of 21-JUN and due date of 28-JUN
PTF date is also 21-JUN
SP1*50009421
SP2*50009423
These appear to be driving the dates for upper level.


EXPECTED BEHAVIOR
----------------------------
Expectation is when we firm the Demand, all Constraints should be ignored and should compress lead times/PTF

BUSINESS IMPACT
----------------------
plan results do not fit business requirements

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms