ECC Plan Planned Replenishment For Expiring Lots Is Not Netting Available Supplies

(Doc ID 2150220.1)

Last updated on JUNE 08, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.3 version, Constrained planning

ACTUAL BEHAVIOR

ECC Plan Planned replenishment for expiring lots is not netting available supplies

Plan is generating almost seemingly to replenish the expiring quantity instead of netting the remaining demands against the remaining supplies.
For example Item has 1000 unit on-hand.
300 units are expiring on July 15th.
There is a 100 units external demand.
In this case there is a remaining quantity of 700 units available to satisfy the demand of 100 units.
However the plan generates a planned order for 300 (or more) to meet the lots that are expiring.
 

EXPECTED BEHAVIOR

Expiring lot should not be considered as demand

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms