Budgeted Material Cost Value Goes to Zero After Assigning Project as a Baseline.

(Doc ID 2151740.1)

Last updated on JUNE 22, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 7.0 5.0 and later
Information in this document applies to any platform.

Symptoms

Budgeted Material Cost value goes to zero after assigning a Project as a Baseline.


STEPS TO REPRODUCE:
-----------------------
The issue can be reproduced at will with the following steps:
1. Open Project, Maintain Baseline, assign Baseline to open Project.
2. Note that before the Baseline is assigned, there are values for BL Project Material Cost, Budgeted Material Cost, and BL Project Total Cost.
3. After the Baseline is assigned, these values are now zero.