Enhancement Request: Is it Possible to Restore/Delete Baselines Without First Unassigning Them? (Doc ID 2152610.1)

Last updated on JUNE 24, 2016

Applies to:

Primavera P6 Professional Project Management - Version 15.2.0.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 15.2.0.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.2.0.0 and later
Information in this document applies to any platform.

Goal

Is it possible to restore/delete a baseline without first unassigning it as a project/primary/etc. baseline?

This can save time if attempting to restore/delete multiple baselines from multiple projects at a single time.
 

Solution