Slow Response When Scheduling or When Adding an Activity or WBS (Doc ID 2156681.1)

Last updated on JULY 06, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.4.11.0 to 16.1.2.0 [Release 8.4 to 16.1]
Information in this document applies to any platform.

Symptoms

These items together cause delays in some operations, as described below:

a) Activities view must be open.
b) The layout for the Activities view Group By must be set to WBS level 2.
c) The Gantt chart must be displayed.

Multiple symptoms may be encountered in P6 Professional:

1.  Adding the first Activity can take minutes.  Subsequent Activity additions are immediate.

2.  Adding the first WBS can take minutes.  Subsequent WBS additions are immediate.

3.  Scheduling the first project can take minutes.  Subsequent Scheduling actions are much faster.


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms