WIP Component items not getting planned in MRP (Doc ID 2157031.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Materials Requirement Planning - Version 12.0.6 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.4 version, Materials Requirements Plan.

ACTUAL BEHAVIOR
---------------

Customer was not seeing demand exploded to a component item, while other components on the same assembly were getting planned

EXPECTED BEHAVIOR
-----------------------
They are expecting a job to be created for WPMFP006BR001 .

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Run the MRP

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot get Jobs for the item.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms