EBS: PS: Incorrect Resource Duration Value within Operation Diagram For an Operation Resource Associated with a Routing within PS (Doc ID 2161361.1)

Last updated on JULY 15, 2016

Applies to:

Oracle Production Scheduling - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

With a User defined UOM as 'd' (DAY) within EBS for an Operation Resource associated with a Routing; PS does convert the UOM 'd' into appropriate number of hours and displays it correctly within the related Work Order>Bill of Resource>Run Time. However, within Operation Diagram the Resource duration is displayed incorrectly and displays the 'Usage' value of UOM set within EBS.

Cause