Duration Values Does Not Match After Imported the Microsoft Project to Agille PPM (Doc ID 2161547.1)

Last updated on AUGUST 08, 2017

Applies to:

Oracle Agile Product Portfolio Management - Version 9.3.4.0 to 9.3.5.0 [Release 9.3]
Information in this document applies to any platform.

Goal

Why Duration Values does not match after importing the Microsoft Project to Agille PPM?

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Import the attached 785 project plan using MS Project save as XML features and Import to PPM. Set the parameter : Set scheduling engine to PPM to checked.
2. Open the Gantt Chartt and review the duration between PPM and MS Project.
3. There is Change in duration values between PPM and MS Project
 

Solution