EDD Plan Suggesting Planned Orders Too Early Causing Resources Overloaded in One Day (Doc ID 2164037.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

On : 12.1.3 version, Constrained planning

 EDD Plan :  Suggested Planned orders created too early causing Resources overloaded in one day

Planned orders has been created with due date :12th July and pegged to sales orders due on 19th July
 

Solution