PPM Web Client Is Not Allowing Update To Duration, However Gantt Chat Is Allowing The Update (Doc ID 2165166.1)

Last updated on AUGUST 08, 2017

Applies to:

Oracle Agile Product Portfolio Management - Version 9.3.4.0 to 9.3.5.0 [Release 9.3]
Information in this document applies to any platform.

Symptoms

On : 9.3.4.0 version, Web client (PPM)

ERROR
-----------------------
PPM Web client is not allowing update to duration, however Gantt chat is allowing the update

Error received while updating (Cannot make the successor date before the predecessor)



STEPS
-----------------------
1. Import the attached project plan into PPM
2. Update the duration for a task, error occur
3. Launch the Gantt chart to update

 

Cause

Sign In with your My Oracle Support account