Error ' Please Provide Valid Project Structure Information for Workplan' After a P6 to EBS via Gateway (Doc ID 2166094.1)

Last updated on AUGUST 03, 2016

Applies to:

Primavera Gateway - Version 15.2.0.0 and later
Information in this document applies to any platform.

Symptoms

On Primavera Gateway, when attempting run a P6 to EBS synchronization using Gateway with the 'Update Actuals' mapping selected, the following error occurs.

Please provide valid Project Structure Information for Workplan


Users cannot complete successfully the P6 to EBS synchronization and transfer the P6 field 'Activity Percent complete' to EBS under Workplan -> Tasks -> P6-Progress

Cause