Start And Finish Date Both Appeared For Milestone Activities In P6 R8.3 Web (Doc ID 2167312.1)

Last updated on JANUARY 09, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.3.2.0 and later
Information in this document applies to any platform.

Symptoms

On : P6 Web Application

ACTUAL BEHAVIOR
---------------
In P6 Web, Start Date is displayed for Finish Milestones and the Finish Date is displayed for Start Milestones (Both dates are displayed no matter if the Activity is a Start or Finish Milestone).

EXPECTED BEHAVIOR
-----------------------
For a Start Milestone Activity the Finish Column should be blank and for Finish Milestone Activity the Start column should be blank, same as in the client.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Open up P6 Web, create a new Project.
2. Add a Start Milestone and a Finish Milestone.
3. Add the Start and Finish columns.
4. Notice that the Start date is populated for the Finish Milestone and the Finish date is populated for the Start Milestone (Both dates are displayed no matter if the Activity is a Start or Finish Milestone).

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms