P6 Web Displays Finish Date For Start Milestones and Start Date for Finish Milestones (Doc ID 2170240.1)

Last updated on AUGUST 19, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 15.2.0.0 and later
Information in this document applies to any platform.

Symptoms


ACTUAL BEHAVIOR
---------------
Start Milestone activity has finish date, vice versa.

EXPECTED BEHAVIOR
-----------------------
Start Milestone activity should not have finish date.  Finish Milestone should not have a start date.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Login P6 Web
2. Go to Projects-->Activities, create new start and finish milestone activities, save it.
3. Find Start and Finish dates are all filled in with values.


BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users see start and finish dates for all milestone activities which is not the same behavior as in the Client application.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms