P6 Baseline Data Is Not Synchronized to Unifier Using Primavera Gateway (Doc ID 2171001.1)

Last updated on AUGUST 24, 2016

Applies to:

Primavera Gateway - Version 15.2.0.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 15.2.0.0 and later
Information in this document applies to any platform.

Symptoms

When synchronizing data from P6 to Unifier using Primavera Gateway, baseline data is not moved from P6 to Unifier. Baselines have been selected for the Send to Unifier action.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. From P6 run the Send to Unifier action for Gateway
2. Select Summary and Spread data under the Summary Sheet section
3. In the list of Projects select baselines to be synchronized under the Baselines column


Cause