When Synchronizing a Project from EBS to P6 Using Primavera Gateway Actuals Are Not Imported (Doc ID 2172388.1)

Last updated on AUGUST 15, 2016

Applies to:

Primavera Gateway - Version 15.1.0.0 and later
Information in this document applies to any platform.

Symptoms

After synchronizing project data from EBS to P6 using Primavera Gateway,  actual quantity and cost are blank. In EBS time cards have been entered and successfully processed. Budget numbers are successfully imported into P6.

STEPS
-----------------------
The issue can be reproduced with the following steps:

1. Setup a project in EBS
2. Synchronize the project to P6 with WBS, resources and activities
3. Enter time cards in EBS
4. Synchronize the project to P6 with WBS, resources and activities
5. While the budget numbers are brought over to P6, the actual quantity and amount are blank

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms