Export Project From PPM To MS Project Task's Cannot Be Differentiated Between Estimated And Actual Date (Doc ID 2176138.1)

Last updated on AUGUST 08, 2017

Applies to:

Oracle Agile Product Portfolio Management - Version 9.3.4.0 and later
Information in this document applies to any platform.

Goal

Why exported XML from PPM only shows Estimated duration?

Steps to reproduce:
1. Export a project from PPM to MS project using the Import \ Export option in PPM
2. Open the exported XML in MS Project - All the duration is displayed in Estimated
 

Solution