Why Start Date And End Date Does Not Match After Import If Taskmode = Manual Schedule (Doc ID 2177286.1)

Last updated on AUGUST 08, 2017

Applies to:

Oracle Agile Product Portfolio Management - Version 9.3.4.0 and later
Information in this document applies to any platform.

Goal

Why Start Date and End Date does not match after Import if Taskmode = Manual schedule

Steps to Reproduce
1. Import the attached project to PPM
2. Validate in highest level node in MS Project is TaskMode = ManualSchedule
3. Import the attached Project plan into PPM ( either PPM Engine and MS Project Engine )
4. Start date and end date does not match
5. Update the highest level node in MS Project is TaskMode = AutoSchedule
6. Import the attached project 2 plan into PPM
7. Start date and end date match.
 

Solution