Symptoms

When attempting to synchronize data from P6 to EBS using Primavera Gateway, the following error occurs.

ERROR
-----------------------
"Invalid Project Operating Unit."

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1. Define the business flow and synchronization job with blank parameter "EBS Responsibility for Project Synch from third party".
2. Run Gateway synchronization job to transfer data from P6 to EBS.
3. Synchronization job fails at the Update Destination step with above error.

Cause

Sign In with your My Oracle Support account