Symptoms

ACTUAL BEHAVIOR
---------------
Projects > Activities shows the Project plus 5 immediate WBS children.

EXPECTED BEHAVIOR
-----------------------
The "Project Statistics" portlet shows the project level plus 9 WBS levels.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. View the project and top level WBS in the activities view (web)
2. View the Project Statistics portlet for the same project

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot trust the data in the portlet as being accurate.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms