When Copying a Project Using P6 Web or P6 Web Services the Integration Project Preferences Are Not Copied (Doc ID 2183421.1)

Last updated on SEPTEMBER 15, 2016

Applies to:

Primavera Web Services - Version 15.1.0.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 15.1.0.0 and later
Information in this document applies to any platform.

Symptoms

When copying a project in P6 Web or using the P6 Web Services CopyProject the Project Preferences for the Integration settings are not copied.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. In P6 Web go to Project Preferences -> Integrations
  2. On the Unifier tab modify any of the following settings:

    Link project to a Primavera Unifier project

    Project name

    Schedule Sheet

    Data Mapping

    Schedule Type (Duration Based / Reesource Loaded / Cost Loaded)

    Delete activities no longer in the P6 Schedule from Primavera Unifier

    Only send activities with CBS codes assigned

    Synchronize WBS Hierarchy

    WBS Hierarchy Type (Complete / Partial / Levels)

  3. On the Gateway tab edit or add the name of the Gateway Deployments. 

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms