Unable To Synchronize Schedule Finish Date From P6 To EBS

(Doc ID 2184130.1)

Last updated on SEPTEMBER 28, 2016

Applies to:

Primavera Gateway - Version and later
Information in this document applies to any platform.


The Scheduled Finish Date mapping is defined in the Field Mapping Template for Project/WBS to sync data from P6 to EBS. But this Finish Date from P6 was not updated to Scheduled Finish Date field on EBS.

<FinishDate xsi:nil="true"/>
<WBS action="create" executed="update" status="success">
<SCHEDULED_FINISH_DATE xsi:nil="true"/>

The Finish Date of P6 project/WBS should be synchronized successfully to EBS as Scheduled Finish Date if these field mappings are defined.

The issue can be reproduced at will with the following steps:
1. Define business flow for transferring data from P6 to EBS with Scheduled Finish Date mappings defined for Project/WBS objects.
2. Run sync job. Planned Finish Date of project/wbs was not synchronized from P6 to EBS as expected.


Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms