Tasks Added By Rules And Behavior Are Not Setting Correct Dates Causing Error "The selected data has violated the task dependency structure and is due date to be completed before its predecessor"

(Doc ID 2185424.1)

Last updated on SEPTEMBER 26, 2017

Applies to:

Oracle Communications MetaSolv Solution - Version 6.2.1 and later
Information in this document applies to any platform.
***Checked for relevance on 26-Sep-2017***

Symptoms

When the user creates a rule for task insertion, in the Task Generation window, the task completion date gets set based on the current date instead of following the completion date of preceding task.


Cause