Tasks Added By Rules And Behavior Are Not Setting Correct Dates Causing Error "The selected data has violated the task dependency structure and is due date to be completed before its predecessor" (Doc ID 2185424.1)

Last updated on SEPTEMBER 22, 2016

Applies to:

Oracle Communications MetaSolv Solution - Version 6.2.1 and later
Information in this document applies to any platform.

Symptoms

When the user creates a rule for task insertion, in the Task Generation window, the task completion date gets set based on the current date instead of following the completion date of preceding task.


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms